During the conversion, Airbus teams install some 16,000 types of new components and approximately 450 new electrical harnesses (for a total cabling length of more than 50 km.), as well as 6,000 brackets and 1,700 connectors.

With 42 A330 MRTTs delivered to date, Airbus’ has reduced the end-to-end transformation time by one month, introducing increased digitalisation and applying the “takt” principle of lean production methodology – in which the aircraft moves through the conversion with zero hours pending and zero work orders open.

The digitalisation includes the increasing use of Microsoft HoloLens mixed reality headsets instead of computer tablets. With 80 to 90 work orders now produced with HoloLens, the goal is to apply the system during 2020 for 50% of overall work orders, mainly for electrical and hydraulic installations.